276%more parts per week after optimisation

Fixture to increase nitriding capacity

A surface-treatment fixture raised nitriding capacity from the original 115 parts to 432 parts per week.

Fixture to increase nitriding capacity

Client

Manufacturing company

Industry

Defence

Timeline

8 weeks

Technologies

Fixture design · Surface treatment · Part placement optimisation

01 — Challenge

Increasing nitriding capacity

The original surface-treatment capacity was 115 parts per week. The goal was to design a fixture that would hold the parts more efficiently throughout the individual processes while meeting the required production capacity.

02 — Solution

Optimised part placement in the fixture

During the design we worked with several part-placement variants and with the requirements of each process. The deciding factor was nitriding, which takes about 18 hours. The final solution made it possible to process the required volume in three nitriding cycles and raise capacity to 432 parts per week.

03 — Approach

01

Process analysis

Evaluating the requirements of each surface-treatment process and the original processing capacity.

02

Design variants

Designing and comparing several part-placement options with regard to capacity, handling and protection of critical surfaces.

03

Final solution

The fixture design achieved a capacity of 432 parts per week in three nitriding cycles.

Technical specifications

Original capacity115 parts / week
New capacity432 parts / week
Capacity increase+276%
Nitriding cycle18 hours

Outcome

432parts per week (a 276% increase)

The new solution increased processing capacity from 115 to 432 parts per week. That is 317 more parts every week, or approximately 276% more than the original capacity.